Starting Wednesday, July 5th, the City's contractor, PCI, will be continuing with construction at the South Main Street and Greenhill Roundabout with removals of temporary pavement and replacement of permanent pavement. In order for the contractor to start work, temporary pavement panels will be removed, and the southbound travel lane of the roundabout will be restricted in width during this removal and replacement operation. Short-term closures of this direction in the roundabout may also take place as workers repave this quadrant. Below is a map of the impacted travel lane.

The restricted width is anticipated to be lifted by Monday, July 10th to vehicular traffic. After July 10th, crews will continue with other curb, truck apron, and landscaping items in the central part of the roundabout.