View the latest Cedar Falls street construction updates for the week of December 13, 2021:
Union Road Recreational Trail
During the week of December 6th, all concrete work has been completed and the trail has had topsoil laid and seeded. Punch list will be created and completed next construction season.
Cedar Heights Drive Reconstruction (Cedar Heights Drive & Greenhill Road)
For the week of December 13th, crews will be continuing with paving operations at the southern half of the Greenhill Road intersection. Crews will also be working on finalizing all approaches to the newly constructed roundabout and at Cedar Hill Road with placement of signs, paint, streetlights, and backfilling operations. Access will be maintained in its current state for this phase of construction until the Cedar Hill intersection is reopened. Traffic on Greenhill will continue in the current pattern for east and westbound traffic until the intersection is fully opened.
Cyber Lane
The Cyber Lane paving has been postponed until Spring. No work was done this week. Temporary erosion control hydromulch was placed on site last week. The contractor has been instructed to add additional rock at the Technology drive intersection (north end of project) for safety. This will be done next week.
West 27th Street Sanitary Sewer Extension
Crews have finalized the project on W. 27th Street with placement of the new sanitary sewer and have completed paving operations. W. 27th is open to traffic. Crews will continue with site stabilization and erosion control over the winter months and into the next spring seeding window.
2021 Permeable Alley Project (9th/10th Street and Main/State Alley and 12th/13th Street and Washington/Main Alley)
For the week of December 6th, this project has been completed and once all paperwork is gathered this project will be closed out.
Learn more about the annual permeable alley project at https://www.cedarfalls.com/1462/Annual-Permeable-Alleys.
Public Sidewalk Repair and Infill Project
During the week of December 6th, Contractor has poured all sidewalk and completed pouring back all driveways. They are waiting on KW to complete the install of the traffic lights (Manufacturing delay).
CDBG Sidewlak Infill Project
During the week of December 6th, Contractor has moved out and plans on coming back next construction season to finish the West 3rd Street Infill.
W. 1st Street/HWY 57 from Franklin Street to Hudson Road
For the week of December 6th, this project has been completed with possible final punchlist work remaining.