News Flash Home
The original item was published from 11/22/2021 10:24:33 AM to 1/2/2022 12:00:03 AM.

News Flash

Our City News

Posted on: November 22, 2021

[ARCHIVED] Cedar Falls Weekly Construction Updates: November 22, 2021

CF Construction updates graphic

View the latest Cedar Falls street construction updates for the week of November 22, 2021:                       

Union Road Recreational Trail          

During the week of November 15th, Van  Dorne crews are finishing paving Sonoma Drive and the remaining Trail. They have the South half of W. 12th Street intersection paved and are working on the North. Lodge construction is working on spreading topsoil and placing hydroseed throughout the site.

Cedar Heights Drive Reconstruction (Cedar Heights Drive & Greenhill Road)

For the week of Thanksgiving, crews will be continuing with paving operations on the southern half of the Cedar Heights and Greenhill intersection near Cedar Hill. A traffic will continue in the current pattern for east and westbound traffic on Greenhill. Crews will also be working on the northbound approach and other handwork locations along Cedar Heights Drive. Access will be maintained in its current state for this phase of construction until the Cedar Hill intersection is reopened.

Cyber Lane

The road is graded, rocked, and trimmed. No pavement yet. There is a jog in the curb line in the southeast area of the site. Consultant to meet on site this coming Monday to verify the alignment.                 

West 27th Street Sanitary Sewer Extension

For the week of Thanksgiving, crews will be continuing with underground sanitary sewer installation work crossing W. 27th Street to the new High School site. Crews anticipate the W. 27th to be fully open shortly after Thanksgiving once paving operations are complete.

2021 Permeable Alley Project (9th/10th Street and Main/State Alley and 12th/13th Street and Washington/Main Alley)

During the week of November 15th, both alleys have been completed and all that is left is punchlist items for this project.     

Learn more about the annual permeable alley project at https://www.cedarfalls.com/1462/Annual-Permeable-Alleys

Public Sidewalk Repair and Infill Project 

During the week of November 15th, Cobalt has wrapped up pouring sidewalk on Hudson Road from W. 8th Street to W. 12th Street and has backfilled along the neew sidewalk. Cobalt will be moving over to Rownd street to start removals and moving quick towards placing the new sidewalk.  

CDBG Sidewlak Infill Project  

During the week of November 15th, OEL has cpmpleted pouring sidewalk on Tuscon Drive, and wrapped up placing topsoil. Matthias is starting to move in to hydroseed and place sod along the infill. Next OEL is moving to W. 3rd street to start the removals of the Eastern infill. 

W. 1st Street/HWY 57 from Franklin Street to Hudson Road  

For the week of Thanksgiving, crews will be finishing the last of punch list items along the corridor from Highland to Franklin. As crews work to finalize the project, sidewalk closures and outside lane closures should be expected for work behind the back of curb. Work will include signage placement, hand railing installation, and sidewalk related work.

Facebook Twitter Email

Other News in Our City News

a-Facebook Cover Earth week 2023

Cedar Falls Earth Week

Posted on: March 13, 2023
People drinking coffee at McDonald's with Cedar Falls officer

Cedar Falls Coffee With a Cop

Posted on: February 15, 2023

Visit the Cedar Falls Art Mural

Posted on: October 26, 2022

Center Street Corridor Streetscape Project

Posted on: September 29, 2022
construction updates graphic

27th Street Reconstruction Phase II

Posted on: September 15, 2022