Stay updated on ongoing street construction projects! Scroll down to receive the latest news and learn what you can expect in the coming week. You can also sign up to receive construction updates (including weekly notices) straight to your email by visiting www.cedarfalls.com/notify and selecting the appropriate project.
Downtown Streetscape:
Removals, subdrain, and electrical conduit are complete at the SE corner of 3rd and Main. The onsite concrete work will take place in this area the week of November 16, with the brick paver contractor following behind. Miscellaneous punch list items remain.
Expected project completion date: Fall 2020
Learn more about the Streetscape project at www.cedarfalls.com/downtown.
West 1st Street/Hwy 57 - Phase 2 (project located West 1st Street/HWY 57-Franklin Street to Hudson Road):
For the week of November 16, traffic will continue to be on the outside lanes between Ellen Street and Walnut Street. Pavement markings and striping will continue into Monday, as weather permits. Traffic control devices are scheduled to be removed later in the week with temporary single-lane closures as the contractor finishes installing roadway signage.
Expected project completion date: Fall 2021
Learn more about the West 1st Street/HWY 57 project at www.cedarfalls.com/Hwy57Expansion.
West 12th Street Reconstruction (project located West 12th - Tremont to College Streets, Walnut - 11th to 12th Streets):
During the week of November 16, the contractor will continue with completing the landscaping, installing handrails, and finalizing their punch list of items. The additional final out items will continue to be addressed by the contractor as the project comes to an end.
Expected project completion date: Fall 2020
Learn more about the West 12th Street Reconstruction Project (part of the Cedar Falls annual street construction program) at www.cedarfalls.com/streetconstructionprogram.
Cedar Falls Permeable Alley Project (project located 4th/5th Street on Tremont and Iowa, 22nd and Seerley on Tremont and Franklin):
The contractor has been working on punch list items. This Project is substantially completed.
Expected project completion date: Fall 2020
Learn more about the Permeable Alley Project at www.cedarfalls.com/PermeableAlleys.
Additional 2020 Annual Street Construction Updates (all projects expected to be completed by Fall 2020):
26th Street (Iowa Street to Tremont Street): Contractor has been working on punch list items. This Project is substantially completed.
Visit www.cedarfalls.com/streetconstructionprogram for more information on the 2020 Annual Street Construction Project.
Additional Construction Note:
Clay Street Park- Water Quality Improvements Project (West 15th Street, Clay Street, West 16th Street): During the week of November 16, the contractor will continue with the final landscaping items such as placement of plantings, placement of mulch, and hydroseeding areas in the park. The contractor will also continue with additional sidewalk placement and new ADA compliant ramps at 15th and Franklin adjacent to the second biocell. Additional final out items will continue to be addressed by the contractor as the project comes to an end.