[ARCHIVED] Cedar Falls Weekly Construction Updates: September 11, 2020

CF Construction updates graphic

Stay updated on ongoing street construction projects! Scroll down to receive the latest news and learn what you can expect in the coming week. You can also sign up to receive construction updates (including weekly notices) straight to your email by visiting www.cedarfalls.com/notify and selecting the appropriate project. 

Construction Updates: September 11, 2020


Downtown Streetscape (project located on 2nd/3rd Street):

West 2nd Street remains completely closed to traffic with the subgrade now rocked and ready for Cunningham to begin preparing the pour. Paving is expected to take two to three weeks- This was originally planned to begin this week but was delayed by the rain. The brick paver contractor is expecting to begin work on the south sidewalk along East 2nd Street as Cunningham finishes the paving on West 2nd Street. Crews will immediately begin work on the W 2nd Street Sidewalks afterward.

Expected project completion date: Fall 2020

Learn more about the Streetscape project at www.cedarfalls.com/downtown

West 1st Street/Hwy 57 - Phase 2 (project located West 1st Street/HWY 57-Franklin Street to Hudson Road): 

Head-to-head traffic will continue on the south lanes between Ellen and Walnut Streets. Crews will continue to work on the sanitary sewer service connection, storm sewer installation, and other related underground utility work between N. Ellen and Pearl Streets. Crews will continue to work towards the east with pavement removal and underground utility work. Temporary driveway access will be provided by the contractor to residential and commercial properties.

Expected project completion date: Fall 2021

Learn more about the West 1st Street/HWY 57 project at www.cedarfalls.com/Hwy57Expansion.

West 12th Street Reconstruction (project located West 12th - Tremont to College Streets, Walnut - 11th to 12th Streets):

West 12th Street is reopened with a few minor finishing touches to be made by PCI contractors. PCI has Walnut rocked and proof roll passed, their structures crew is now pouring the retaining wall on top of the sidewalk.

Expected project completion date: Fall 2020

Learn more about the West 12th Street Reconstruction Project (part of the Cedar Falls annual street construction program) at www.cedarfalls.com/streetconstructionprogram. 

Cedar Falls Permeable Alley Project (project located 4th/5th Street on Tremont and Iowa, 22nd and Seerley on Tremont and Franklin):

4th/5th Street Alley has both collars in and brick work completed. Currently waiting on seeding everywhere that has been regraded adjacent to the new alley. 22nd/Seerley Alley has both collars poured and the South Approach. Cunningham has poured the concrete patch back on 22nd Street and Aspro is going to complete the HMA lift next.

Expected project completion date: Fall 2020

Learn more about the Permeable Alley Project at www.cedarfalls.com/PermeableAlleys.

Additional 2020 Annual Street Construction Updates (all projects expected to be completed by Fall 2020):

26th Street - Iowa Street to Tremont Street: Storm sewer work ongoing along 26th St. Water main is currently being installed at the intersection of 26th and Tremont.

Lilac Lane - Rownd St. to McClain Dr.: Street is closed from Rownd to 600’ west. Lilac Lane is being prepared for paving operations to begin next week and Cunningham Construction is currently planning on paving the mainline pour for Lilac on September 17.

Madison Street- Valley Park to Waterloo Road: Street is currently closed from Valley Park to Whiteway. Madison Drive is being prepared for paving operations to begin next week. Cunningham Construction is currently planning on paving the mainline pour for Madison next Tuesday, followed by a 1/2 intersection hand-pour at White Way Drive. 

11th Street - Division Street to College Street: Asphalt paving has been completed. Topsoil and sod/seed scheduled for placement.

Union Road - 1st St./HWY 57 to N.C.L: Complete. 

Note, construction on the following streets listed as part of the 2020 Annual Street Program are complete: Clearview Drive (Primerose to Orchard), Chateau Court (4th Street to Cul-de-sac), Holmes Drive (4th Street to Holmes Junior High), Carlton Drive (Lilac Lane to Maplewood Drive), Seerley Blvd. (Valley Park to Melrose Drive), Ashland Ave. (Acorn Lane to Pin Oak Drive). 

Visit www.cedarfalls.com/streetconstructionprogram for more information on the 2020 Annual Street Construction Program. 

Facebook Twitter Email

Other News in Our City News

Career Fair 2024 text on gray background

City of Cedar Falls To Host Career Fair

Posted on: February 28, 2024
public parking meeting text

Cedar Falls to Host Public Meetings for Downtown Parking

Posted on: February 8, 2024 | Last Modified on: May 16, 2023
Parking survey quick read code

Cedar Falls Downtown Parking Survey

Posted on: February 19, 2024 | Last Modified on: May 16, 2023
picture of a bulldozer

Traffic Signal Work - Ridgeway Avenue

Posted on: February 25, 2024 | Last Modified on: May 16, 2023

Road Closure Notice: Rownd Street

Posted on: February 24, 2024
Public Meeting FB 2020

Public Information Meeting: 2024 Street Restoration and Alley Reconstruction Project

Posted on: February 22, 2024 | Last Modified on: May 16, 2023
Acting Chief Mark Howard sitting with citizens during coffee with a cop

Coffee With a Cop Events

Posted on: February 1, 2024

Sidewalk Scaffolding - East 4th Street

Posted on: January 22, 2024
CF Press Release

Winter Safety Reminders

Posted on: January 8, 2024

Trail Closure - South Riverside Trail

Posted on: December 27, 2023
overhead shot of the cedar river

Cedar River Recreational Project Update

Posted on: December 21, 2023
TC panther mascot with a family

Panthers on Parade

Posted on: August 29, 2023
Kids sitting in a row with firefighters

Cedar Falls Hosts Youth Fire Academy

Posted on: August 2, 2023
Fireworks allowed from 9 AM to 10 AM on July 3 and From 9 AM to 11 AM on July 4 (text)

Cedar Falls Fireworks Ordinance

Posted on: June 2, 2023
construction updates graphic

27th Street Reconstruction Phase II

Posted on: September 15, 2022