Beginning Monday, May 18th, multiple closures will be placed in the area around 3rd and Main Street. The three new closures are listed below.

The contractor will begin reconstructing the sidewalk on the south side of West 3rd Street. To perform this work, a sidewalk closure will be in effect for six (6) to eight (8) weeks.

The contractor will begin patching the intersection of 3rd and Main Street. To perform this work, a single lane closure will be in effect from Monday to Wednesday (18th – 20th).

DCI Group will be working on the west side of the new construction at 302 Main Street. To perform this work, a sidewalk closure will be in effect for three (3) weeks.

Above you will find a map of the closure areas.

Regards,

Benjamin Claypool, Civil Engineer II, PhD, EI

The City of Cedar Falls logo

City of Cedar Falls

Public Works | Engineering Division 

220 Clay Street | Cedar Falls, Iowa 50613

Phone: (319) 243-2704

E-mail: benjamin.claypool@cedarfalls.com